The following checklist documents activities that should be considered during project execution.
Table 98 - Checklist - Project Execution
No |
Item Description |
Comments |
√ |
|
SPCS Vendor should create a project specific MDIS Interface specification for DCS. |
This MDIS Interface specification should be based on documented FEED discussions. |
|
|
SPCS Vendor to schedule date for delivery of MDIS NodesetFile(s) for DCS Vendor. |
More than one date might be scheduled, where each date would provide a NodesetFile that includes additional object definitions. For example, an initial NodesetFile might contain just the first prototype of a well, and subsequent NodesetFiles might contain a more detailed well and then multiple instances of the well. Also, some Objects might include additional optional items as the well model is finalized. |
|
|
Schedule date for first MDIS interface connection Test. SPCS vendor, DCS vendor and Operator should agree on test cases for first MDIS interconnection test. |
First interconnection test should cover test cases such as redundancy, time synchronization, performance, etc. |
|
|
Check possibility/availability of an online SPCS OPC UA MDIS Server to support and accelerate interface development. |
Operator to support/provide infrastructure (e.g. use own infrastructure or cloud systems) if link between SPCS and DCS Vendor cannot be established. |
|
|
DCS Vendor to prepare Interface Test procedure. Schedule review cycle for Operator and SPCS vendor. |
|
|
|
Schedule Date for final MDIS interface connection Test (full project configuration, including sequences and interlocks, etc.). |
|
|